Septic design engineer conducts soils testing, generates written soils test report, and septic design
Estimate for project will be provided
Once estimate is approved, Douglas County Septic will complete permit application and submission to the local county health department for new installation or repair(s)
Upon issuance of repair permit, installation process may begin
Douglas County Septic will schedule installation & utility locates will be scheduled
Local county health department will inspect & approve system installation and or repair(s)
System will be backfilled and graded appropriately and any new seeding of the area is done.
Permit is completed by local health department or septic engineer and provided to property owner and installer